This project was for a customer in Belgium who was expanding operations and building a brand new second line warehouse.
The site started as a greenfield site and Air Tech were asked to provide cargo handling equipment.
Working with both the customer and building architects, Air Tech ensured the project would run smoothly.
The project was a mixture of powered and manual equipment involving truck dock scissor lifts and build stations.
Project Totals | Qty |
Truck Dock | 4 |
Build Station | 4 |
Castor Deck Area (ft²) | 18,428 |
Powered Roller Bed Length (ft) | 62.34 |
Barrier Length (ft) | 931.76 |
Walkway Area (ft²) | 667.4 |
Finger Stops | 1584 |
Weigh Scales | 4 |